The Music Centre will be constructed using an alliance model based on shared responsibility. In the alliance, the City of Turku partners with Hartela, PES-Architects and WSP Finland, with Laidun design as a subcontractor. The parties to the alliance are jointly responsible for implementing the project objectives.
A site camera at the Music Centre Fuuga site follows the progress of construction. The roof of the adjacent government office building provides an extensive view of the entire riverbank and over the construction site. The photo is updated with an hour’s delay.
Construction schedule
-
2020 decision on location
-
October-November 2023
- Earthworks
-
Beginning of 2024
- Blasting and piling completed
-
Spring 2024
- Foundations completed
-
ActiveBeginning of 2025
- Building frame completed
-
ActiveAutumn 2025
- Façades and roofing completed
-
ActiveSpring 2026
- Finishing works completed
-
Autumn 2026