Turku Music Hall Fuuga will be built on the eastern bank of the Aura River, next to Turku City Theatre. Construction began in autumn 2023, and the building is set for completion in 2026.

Follow the project

Stay up to date on construction and its impacts, including on traffic

Built using an alliance model

The Music Hall will be constructed using an alliance model based on shared responsibility. In the alliance, the City of Turku partners with Hartela, PES-Architects and WSP Finland, with Laidun design as a subcontractor. The parties to the alliance are jointly responsible for implementing the project objectives.

A site camera at the Music Hall Fuuga site follows the progress of construction. The roof of the adjacent government office building provides an extensive view of the entire riverbank and over the construction site. The photo is updated with an hour’s delay.

Construction schedule

  • 2020 decision on location
  • October-November 2023
    • Earthworks
  • Beginning of 2024
    • Blasting and piling completed
  • Spring 2024
    • Foundations completed
  • Active
    Beginning of 2025
    • Building frame completed
  • Active
    Autumn 2025
    • Façades and roofing completed
  • Spring 2026
    • Finishing works completed
  • Autumn 2026
    • Fuuga opens to the public